This project is to be installed in U Block, Phase 8, DHA, Lahore
End to end 8 days time
Description
Scope:
- Panel Installation L2/L3 structure aesthetically
- Electric connectivity including MC4 installation and inverter commissioning
- Conduit fixing and Breaker Box installation
- Cut Off Switch installation
- Lightening Arrestor installation
- WiFi portal configuration
- Earth connectivity
Milestones already Achieved:
- Inverter Huawei 10KTL installed
- Inverter Fronus 6kW installed
- Panels shifted to rooftop
- DC Cables laid already